July 2019
- Report Date
- July 2019
Achievements in Last Period
- Deployment milestone completed successfully well within scheduled outage window on 02/07/19.
- Project team have set up monitoring on all Moodle environments and provided access to Production Management colleagues to assist troubleshooting service issues.
- Deployment Sign Off Review (DSOR) milestone completed successfully 18/07/19.
- Closure report circulated w/c 29/07/19.
Issues
- No issues.
Next Steps
- Project closure.
Milestones
| Close | 02-Aug-2019 |
Project RAG status is currently GREEN. Closure delayed by a week (resource conflict on PM and other team members).
- Approved budget
- 75.0 days
- Activity this month
- 6.9 days
- Activity this year
- 39.8 days
- Activity to date
- 39.8 days
- Estimate to complete current year
- 12.6 days
- Estimate to complete future years
- 0.0 days