June 2019
- Report Date
- June 2019
Achievements in Last Period
- Moodle source code integrated into GIT and Bamboo. New process now in place for deployment through Dev / Test / Live.
- UAT completed with no emergent showstopper issues.
- Acceptance milestone provisionally signed off in team meeting 27/06/19 subject to 2 emergent issues being addressed; one was related to a cron loggin error (root cause identified and resolved 28/06/19), the second was related to intermittent performance issues on the Test platform: DevTech have spent time investigating the performance issues and are confident they are not related to changes introduced by upgrades to Moodle - this was discussed by a sub section of the project team on 28/06/19 and agreed that if no other issues emerged then the deployment would continue as planned on 02/07 with the knowledge that it could be rolled back quickly if necessary.
- TAD updates to be completed before DSOR.
- Deployment milestone completed successfully well within scheduled outage window on 02/07/19.
Issues
- No issues.
Next Steps
- DSOR and project closure.
Milestones
| Deployment Sign Off Review (DSOR) | 18-Jul-2019 |
| Close | 02-Aug-2019 |
Project RAG status is currently GREEN.
- Approved budget
- 75.0 days
- Activity this month
- 6.9 days
- Activity this year
- 39.8 days
- Activity to date
- 39.8 days
- Estimate to complete current year
- 12.6 days
- Estimate to complete future years
- 0.0 days