May 2019

Report Date
May 2019

Achievements in Last Period

  • Test upgrade delayed in agreement with project team in order to take in next Moodle point release, and work to integrate Moodle source code into GIT and Bamboo.
  • Test upgrade complete.
  • Significant work  required on the theme; almost all changes now deployed to Dev and pushed through to Test; final  theme changes expected by w/c 12/06/19 in order that UAT commence.

Issues

  • No major issues. Project running slightly behind initial timeline due to additional time required to set up GIT and Bamboo deployment process; this is now in place and there are no major issues with testing so the business is comfortable with the time available for UAT. 

Next Steps

  • UAT and any necessary jira fixes.
  • Review estimates.

 

Milestones

Acceptance 28-Jun-2019
Deployment 12-Jul-2019
Deployment Sign Off Review (DSOR) 02-Aug-2019
Close 16-Aug-2019

 

Project RAG status is currently GREEN.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project RAG status is currently GREEN.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
9.1 days
Activity this year
29.8 days
Activity to date
29.8 days
Estimate to complete current year
31.3 days
Estimate to complete future years
1.0 day

Project Info

Project
Moodle Upgrade
Code
TEL059
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Karen Howie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-Jan-2019
Planning Date
15-Feb-2019
Delivery Date
02-Jul-2019
Close Date
02-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation