March 2019
- Report Date
- March 2019
Achievements in Last Period
- Analysis & Design milestone approved w/c 04/03/19.
- Build tasks delayed by a few days to enable the most recent release 3.4.8 to be used (released 11 March) (this was agreed by project team).
- Signoff of Build milestone expected w/c 01/04/19.
- Members of the project team met with colleagues in SW Dev and agreed on an approach to bring the code into version control; this to be implemented following signoff of Dev.
Issues
- No major issues. Project running to expected timeline.
- Initial test of Moodle Mobile functionality on Dev proved negative.
Next Steps
- Complete Build on Dev.
- Checkpoint for committing to Moodle version.
- Review estimates.
Milestones
| Build | 29-Mar-2019 |
| Integration | 12-Apr-2019 |
| Acceptance | 28-Jun-2019 |
| Deployment | 12-Jul-2019 |
| Deployment Sign Off Review (DSOR) | 02-Aug-2019 |
| Close | 16-Aug-2019 |
Project RAG status is currently GREEN.
- Approved budget
- 50.0 days
- Activity this month
- 2.6 days
- Activity this year
- 4.3 days
- Activity to date
- 4.3 days
- Estimate to complete current year
- 70.0 days
- Estimate to complete future years
- 0.0 days