March 2019

Report Date
March 2019

Achievements in Last Period

  • Analysis & Design milestone approved w/c 04/03/19.
  • Build tasks delayed by a few days to enable the most recent release 3.4.8 to be used (released 11 March) (this was agreed by project team).
  • Signoff of Build milestone expected w/c 01/04/19.
  • Members of the project team met with colleagues in SW Dev and agreed on an approach to bring the code into version control; this to be implemented following signoff of Dev. 

Issues

  • No major issues. Project running to expected timeline.
  • Initial test of Moodle Mobile functionality on Dev proved negative.

Next Steps

  • Complete Build on Dev.
  • Checkpoint for committing to Moodle version.
  • Review estimates.

 

Milestones

Build 29-Mar-2019
Integration 12-Apr-2019
Acceptance 28-Jun-2019
Deployment 12-Jul-2019
Deployment Sign Off Review (DSOR) 02-Aug-2019
Close 16-Aug-2019

Project RAG status is currently GREEN.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project RAG status is currently GREEN.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
2.6 days
Activity this year
4.3 days
Activity to date
4.3 days
Estimate to complete current year
70.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Moodle Upgrade
Code
TEL059
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Karen Howie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-Jan-2019
Planning Date
15-Feb-2019
Delivery Date
02-Jul-2019
Close Date
02-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation