January 2019
- Report Date
- January 2019
Achievements in Last Period
- Project Initiated.
- Project Sponsor and Team kickoff meeting held 25/01/19.
- Project Team confirmed.
- Weekly Team meetings in place starting 31/01/19.
- Draft Project Brief available.
- Draft BRD available.
Issues
- No issues. Awaiting DevTech assessment of latest stable Moodle release documentation to determine any version dependencies with supporting software.
Next Steps
- Scope to be confirmed.
- Agree scope and work with TechMan, DevTech, SWDev on planning and estimates.
Milestones
To be determined during planning
| End of Planning | 15-Feb-2019 |
| Analysis & Design | 01-Mar-2019 |
| Build | 29-Mar-2019 |
| Integration | 12-Apr-2019 |
| Acceptance | 28-Jun-2019 |
| Deployment | 12-Jul-2019 |
| Deployment Sign Off Review (DSOR) | 02-Aug-2019 |
| Close | 16-Aug-2019 |
Project RAG status is currently GREEN.
- Approved budget
- 50.0 days
- Activity this month
- 1.5 days
- Activity this year
- 1.5 days
- Activity to date
- 1.5 days
- Estimate to complete current year
- 74.0 days
- Estimate to complete future years
- 0.0 days