Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
- Learn MyEd channel deployed to live.
- BI data feed deployed but still pointing to 2018/19 data.
- Setup of SaaS staging environment ongoing.
- 'Implementation of Data Retention Policy' work has been deployed to Dev environment.
- Further preparation for testing of new bb_stats schema.
- Project Sponsor has changed from Anne-Marie Scott to Karen Howie.
- Project Manager has changed from Sonali Nokhate to Karen Beggs.
Issues
- None
Next Steps
- SaaS Staging environment to be completed - BBL feeds schema to be exported from Dev to Test, then Live to Test.
- DevTech to investigate / resolve BI feed issue (unable to connect to Learn remote database) to enable final testing and handover.
- 'Implementation of Data Retention Policy' to be tested.
- Learn MyEd channel caching to be looked at by DevTech team.
Milestones
| Deployment to Live - Phase 2 | 31-Jan-2020 | 30-Nov-2019 | No | |
| Project Closure | 14-Feb-2020 | 13-Dec-2019 | No |
- Approved budget
- 470.0 days
- Activity this month
- 21.4 days
- Activity this year
- 153.6 days
- Activity to date
- 435.2 days
- Estimate to complete current year
- 29.0 days
- Estimate to complete future years
- 0.0 days