Report for November 2019
- Report Date
- November 2019
Achievements in Last Period
- Testing completed of Learn MyEd channel, deployment scheduled for 11th Dec, post change freeze period.
- Testing of BI data feed in progress. Plan to deploy it to live before Christmas if testing is successful.
- Setup of SaaS staging environment ongoing.
- Design and Development of 'Implementation of Data Retention Policy' work in progress.
- Local database created for storing data from self-hosted Learn's bb_stats schema.
Issues
- None
Next Steps
- Deploy Learn MyEd channel to Live.
- Complete testing of BI feed and deploy to Live.
- Complete setup of SaaS staging environment.
- Complete development work for 'Implementation of Data Retention Policy' strand of work.
Milestones
| Deployment to Live - Phase 2 | 31-Jan-2020 | 30-Nov-2019 | No | |
| Project Closure | 14-Feb-2020 | 13-Dec-2019 | No |
- Approved budget
- 470.0 days
- Activity this month
- 28.2 days
- Activity this year
- 132.5 days
- Activity to date
- 414.0 days
- Estimate to complete current year
- 31.3 days
- Estimate to complete future years
- 0.0 days