Report for October 2019
- Report Date
- October 2019
Achievements in Last Period
- Testing uncovered some issues with Learn MyEd channel, investigation work ongoing.
- Development work for final solution for BI data feed complete and ready for testing. LTW awaiting access to Test TELSMI.
- Setup of SaaS staging environment ongoing.
- Business Requirements document created for 'Implementation of Data Retention Policy' work. Awaiting revised estimates from Software Development.
Issues
- None
Next Steps
- Complete testing of Learn MyEd channel changes and deploy to Live.
- Complete testing of BI feed.
- Complete setup of SaaS staging environment.
- Start development work for 'Implementation of Data Retention Policy' strand of work.
Milestones
| Planning Complete | 06-Dec-2018 |
| Complete R&D Phase | 31-Jan-2019 |
| Data Cleansing Complete for Test Migration | 22-Mar-2019 |
| Provide Test Migration Data to Blackboard | 02-Apr-2019 |
| Start Test Migration | 05-Apr-2019 |
| Build ready for Test migration | 23-Apr-2019 |
| Handover of Production Saas from Blackboard to UoE | 26-Apr-2019 |
| Complete Build | 20-May-2019 |
| End Test Migration | 24-May-2019 |
| Go/No-Go Decision | 31-May-2019 |
| Complete User Acceptance Testing | 14-Jun-2019 |
| Deployment to Live - Phase 1 | 17-Jul-2019 |
| Deployment Review - Phase 1 | 09-Aug-2019 |
| Deployment to Live - Phase 2 | 30-Nov-2019 |
| Project Closure | 13-Dec-2019 |
- Approved budget
- 440.0 days
- Activity this month
- 52.5 days
- Activity this year
- 0.0 days
- Activity to date
- 383.5 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days