Report for October 2019
- Report Date
- October 2019
Achievements in Last Period
- It was agreed at the DSOR 29/08/19 that the project could not yet close due to issues which have come up in the period post deployment. Closure milestone date moved to 31/10/19.
- The emailing from assessments issue has been recognised as a known issue by Questionmark: they have proposed to resolve this with an upgrade to the application; it has been agreed that this upgrade be carried out by Questionmark but would need to be scheduled for the Christmas period and would be in service.
- It was requested that DR testing be carried out before project closure however the outcome of discussion with ITI was proposal to move on to the stretch cluster, given that DR has been verified on the platform.
Issues
- There remain two issues preventing project closure; there is a plan to resolve both of these (one within the project, the other in service).
Next Steps
- Ensure platform is on infrastructure with verified level of DR.
- Decommissioning of legacy QMP platform / update of TAD / Deployment checklists completed.
Milestones
|
05-Oct-2019 |
|
|
31-Oct-2019 |
Rag commentary: Project is AMBER
Overall RAG being flagged as AMBER as there are open issues preventing closure.
- Approved budget
- 119.0 days
- Activity this month
- 1.4 days
- Activity this year
- 7.3 days
- Activity to date
- 140.3 days
- Estimate to complete current year
- 6.6 days
- Estimate to complete future years
- 0.0 days
