TEL039 WebPA Migration - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2016 BLUE 40.0 days 41.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 13 June 2016
Close Date
Friday, 3 February 2017
Project information
Project Code
TEL039
Programme
ISG - Technology Enhanced Learning (TEL)
Session
16/17
15/16
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Overall Priority
Normal