Report for July 16

Report Date
July 2016

Achievements in the last period

  • Acceptance completed and sign off achieved on 30th June
  • Deployment to Live completed  as planned on 12th July only a slight delay in the deployment start time due to outage encountered at AT.
  • DSOR meeting held on 28th July
  • Closure completion report drafted and closure questionnaire issued out for lessons learned.

 

Issues

  • No major issues since deployment to live
  • Updated and tested DR plan not completed so this is scheduled for week commencing 1st August

 

Next steps

  • Closure sign off
  • Project Closure

 

The project status is GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
58.0 days
Activity this month
6.0 days
Activity this year
35.0 days
Activity to date
35.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
1.0 day

Project Info

Project
Annual Moodle Upgrade
Code
TEL030
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
05-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Aug-2016
Category
Compliance