May 2016
- Report Date
- May 2016
Achievements in the last period
- Test platform upgraded and refreshed.
- Load / capacity testing planned w/c 06/06/16.
- Liaison with TEL025 PM to ensure testing can progress on Moodle test.
Issues
- No major issues at present.
Next steps
- Testing, UAT, and progress to Acceptance as per the plan.
Milestones
24-Jun-2016 | Acceptance |
11-Jul-2016 | Deployment |
22-Jul-2016 | Deployment Sign Off |
29-Jul-2016 | Project Closure |
- Approved budget
- 58.0 days
- Activity this month
- 8.0 days
- Activity this year
- 23.0 days
- Activity to date
- 23.0 days
- Estimate to complete current year
- 32.0 days
- Estimate to complete future years
- 0.0 days