April 2016
- Report Date
- April 2016
Achievements in the last period
- We have progressed into the Build phase of the project.
- Dev has been refreshed from Live and Moodle has been updated.
- We are working through testing on Dev as per our plan.
- We will now take the work of TEL025 through the environments at the same time as the Moodle Upgrade.
Issues
- There have been some issues surrounding resourcing, but we have been resolving these satisfactorily as they occur.
- Some plugins have created fatal errors in Dev, but the Service Owner along with support from Software Dev have resolved the issues.
Next steps
- Progress into Test as per the plan.
Milestones
29-Apr-2016 | Build |
24-Jun-2016 | Acceptance |
11-Jul-2016 | Deployment |
22-Jul-2016 | Deployment Sign Off |
29-Jul-2016 | Project Closure |
- Approved budget
- 58.0 days
- Activity this month
- 6.9 days
- Activity this year
- 16.1 days
- Activity to date
- 16.1 days
- Estimate to complete current year
- 41.9 days
- Estimate to complete future years
- 0.0 days