March 2016

Report Date
March 2016

Achievements in the last period

  • The BRD has been drafted and circulated for sign off.
  • Although slightly out of sync Software Development have started the analysis of the new version and the SDS is being updated.  This is helping to keep us on track as we get the BRD signed off.

Issues

  • Other than a delay in getting the BRD signed off due to Annual Leave and illness we are on track.  We do not anticipate this will delay the plan as a whole.

Next steps

  • We will sign off the Analysis and Design phases of the project.
  • We will refresh DEV and install the updated version of Moodle.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
58.0 days
Activity this month
2.5 days
Activity this year
9.2 days
Activity to date
9.2 days
Estimate to complete current year
48.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Moodle Upgrade
Code
TEL030
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
05-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Aug-2016
Category
Compliance