March 2016
- Report Date
- March 2016
Achievements in the last period
- The BRD has been drafted and circulated for sign off.
- Although slightly out of sync Software Development have started the analysis of the new version and the SDS is being updated. This is helping to keep us on track as we get the BRD signed off.
Issues
- Other than a delay in getting the BRD signed off due to Annual Leave and illness we are on track. We do not anticipate this will delay the plan as a whole.
Next steps
- We will sign off the Analysis and Design phases of the project.
- We will refresh DEV and install the updated version of Moodle.
- Approved budget
- 58.0 days
- Activity this month
- 2.5 days
- Activity this year
- 9.2 days
- Activity to date
- 9.2 days
- Estimate to complete current year
- 48.8 days
- Estimate to complete future years
- 0.0 days