January 2016
- Report Date
- January 2016
Achievements in the last period
- We have completed the planning phase for the project subject to a clarification of the stakeholder from the o365 Service team.
- We are also providing an estimation of the effort required from the Service Owner.
Issues
- None
Next steps
- We now move on with the execution of the project work.
- Approved budget
- 50.0 days
- Activity this month
- 2.3 days
- Activity this year
- 2.5 days
- Activity to date
- 2.5 days
- Estimate to complete current year
- 47.5 days
- Estimate to complete future years
- 0.0 days