December 2015

Report Date
December 2015

Achievements in the last period

  • The project was initiated in the last week of December.
  • Initial meeting have been setup and a draft brief has been created based on previous projects.
  • We know that due to the limitations of the current infrastructure we cannot enhance the current disaster resilience, however we are able to investigate enhancing the capacity of the service and we will do this through planning so that we are clear on the project scope.

Issues

  • TEL025 is currently utilising the DEV and TEST Moodle environments.  Although we expect this project to proceed ahead of our developments it is worth noting this project is in progress.

Next steps

  • As mentioned above we will proceed with the planning.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
0.2 days
Activity this year
0.2 days
Activity to date
0.2 days
Estimate to complete current year
49.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Moodle Upgrade
Code
TEL030
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
05-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Aug-2016
Category
Compliance