Report for June 16

Report Date
June 2016

Achievements

  • Iteration 3 materials delivered to CogBooks on time – now in their QA process

Issues

  • No further updates from lead editor on feedback survey – assuming this has not been delivered and will go into closure as a deliverable not achieved

Next steps

  • Waiting on CogBooks updating us with regards to contract costs
  • DSOR – 25 July
  • Close 29 July

 

Milestones

25-Jul-2016Deployment review
29-Jul-2016Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
1.0 day
Activity this year
19.0 days
Activity to date
19.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Adaptive Learning Pilot
Code
TEL029
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Sue Woodger
Project Sponsor
Jo Spiller
Current Stage
Close
Status
Closed
Start Date
02-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Overall Priority
Normal
Category
Discretionary

Documentation