Report for May 16

Report Date
May 2016

Achievements

  • Iteration 3 materials are in development
  • PM met with CogBooks PM – he is looking into licensing going forward
  • Project sponsor approved the revised milestones so iteration 3 could be completed and additional 7 days budget for the project to cover PM time until end of July. Eduardo agreed 21 June would be when iteration 3 materials would be complete and submitted to CogBooks so the revised milestones were
    • Development of iteration 3 materials - Internal signoff - 19 July
    • DSOR – 25 July
    • Close 29 July

Issues

  • Feedback survey is still delayed. TEL set the surveys up for Lead editor and registered his uun for access then handed the surveys over to him as he wanted to do them and TEL have heard nothing more. PM is following up with lead editor and milestone has been delayed further until 13 June.

Next steps

  • Feedback on surveys from lead editor
  • Iteration 3 materials to be submitted to CogBooks by 24 June

 

RAG: green - agreed with project sponsor

 

Milestones

13-Jun-2016Feedback survey updates deployment
19-Jul-2016Development of iteration 3 coursework materials - internal signoff
25-Jul-2016Deployment review
29-Jul-2016Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
1.0 day
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
12.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Adaptive Learning Pilot
Code
TEL029
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Sue Woodger
Project Sponsor
Jo Spiller
Current Stage
Close
Status
Closed
Start Date
02-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Overall Priority
Normal
Category
Discretionary

Documentation