Report for May 16
- Report Date
- May 2016
Achievements
- Iteration 3 materials are in development
- PM met with CogBooks PM – he is looking into licensing going forward
- Project sponsor approved the revised milestones so iteration 3 could be completed and additional 7 days budget for the project to cover PM time until end of July. Eduardo agreed 21 June would be when iteration 3 materials would be complete and submitted to CogBooks so the revised milestones were
- Development of iteration 3 materials - Internal signoff - 19 July
- DSOR – 25 July
Close 29 July
Issues
- Feedback survey is still delayed. TEL set the surveys up for Lead editor and registered his uun for access then handed the surveys over to him as he wanted to do them and TEL have heard nothing more. PM is following up with lead editor and milestone has been delayed further until 13 June.
Next steps
- Feedback on surveys from lead editor
- Iteration 3 materials to be submitted to CogBooks by 24 June
RAG: green - agreed with project sponsor
Milestones
| 13-Jun-2016 | Feedback survey updates deployment |
| 19-Jul-2016 | Development of iteration 3 coursework materials - internal signoff |
| 25-Jul-2016 | Deployment review |
| 29-Jul-2016 | Close |
- Approved budget
- 30.0 days
- Activity this month
- 1.0 day
- Activity this year
- 18.0 days
- Activity to date
- 18.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days