Report for April 16
- Report Date
- April 2016
Achievements
- Nothing this month
Issues
- Meeting was held with project sponsor and programme manager where project manager discussed her concerns for the delivery of iteration 3 materials, even if the project is extended to end July 16. Closure is currently due next week on 3 May and we are awaiting formal approval from project sponsor that she agrees to an extension of the project and an additional 7 days budget. A piccl has been submitted for an interim closure date until that approval is received.
- Feedback survey is still delayed. There has been confusion with the Lead editor about who is doing this work. He has been informed again to liaise with Amy Woodgate. He says that they will aim to get the survey out during exams and is confident that they will get a good response. PM has asked Amy to liaise with Lead Editor to ensure survey goes out. Milestone has been delayed until 13 May.
Next steps
- Feedback on updates to the existing surveys to be sent to Amy so she can update the surveys
- Agreement reached on iteration 3
Project is AMBER as although we have approved milestones they are only interim. We await project sponsor approval to get the milestones finalised.
Milestones
13-May-2016 | Feedback survey updates deployment | |
16-May-2016 | Deploy iteration 3 coursework materials | |
16-May-2016 | Development of iteration 3 coursework materials - internal signoff | |
20-May-2016 | Deployment review | |
23-May-2016 | Close |
- Approved budget
- 23.0 days
- Activity this month
- 3.0 days
- Activity this year
- 17.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days