Report for February 16

Report Date
February 2016

Achievements

Issues

 

Next steps

 

Milestones

28-Mar-2016Feedback survey updates deployment 
04-Apr-2016Development of iteration 3 coursework materials - internal signoff 
11-Apr-2016Deploy iteration 3 coursework materials 
27-Apr-2016Deployment review 
03-May-2016Close 
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
3.0 days
Activity this year
12.0 days
Activity to date
12.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Adaptive Learning Pilot
Code
TEL029
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Sue Woodger
Project Sponsor
Jo Spiller
Current Stage
Close
Status
Closed
Start Date
02-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Overall Priority
Normal
Category
Discretionary