Report for November 2015
- Report Date
- November 2015
Achievements in Last Period
Project plan and brief is with the project team for agreement. Once agreed will ensure CogBooks are in line with the plan and it can then go for sign off
SMEs have already started work on the updates to current materials
Issues
None so far
Next Steps
Project Brief to be signed off
Milestones
11-Dec-2015 | Planning |
13-Jan-2016 | Analytics Configuration Semester 2 |
13-Jan-2016 | Update current coursework materials |
15-Jan-2016 | Deploy current coursework materials updates |
18-Jan-2016 | Development of new materials |
18-Jan-2016 | Deploy Analytics Semester 2 |
22-Jan-2016 | Deploy new materials |
15-Feb-2016 | Analytics Configuration Semester 1 |
19-Feb-2016 | Feedback Survey results updates |
22-Feb-2016 | Deploy Analytics Semester 1 |
31-Mar-2016 | Feedback Survey results new materials |
11-Apr-2016 | Deployment review |
18-Apr-2016 | Close |
- Approved budget
- 20.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days