February Report
- Report Date
- February 2016
Achievements in Last Period
- Build review sign off achieved
- Deployment to test completed and Integration testing signed off
- Commence UAT by Moodle Service team
Issues
- Build review sign off delayed: data source cretaed, peer testing fixes resolved and clarity on course code information finalised with Student Systems before agreement to move to Integration.
- Final confirmation on using existing Grouper information on course code provided by Student Systems
- Review current milestones following completion of Integration testing - this was delayed due to database refresh from Live to resolve a Service Issue and also key resource - Moodle Service manager on leave when deployment to live is targetted so the project team will complete a review of testing progress and agree a revised date.
- Review impacts of delays on project budget
Next Steps
- UAT to complete and sign off Acceptance
- Deployment Checklist
- Preparation for deployment – checklist, service alert etc.
- Deployment to Live
The project status is currently AMBER due to possible changes to milestones and budget.
10-Mar-2016 | |
17-Mar-2016 | |
24-Mar-2016 | |
31-Mar-2016 |
- Approved budget
- 58.0 days
- Activity this month
- 9.1 days
- Activity this year
- 53.3 days
- Activity to date
- 57.4 days
- Estimate to complete current year
- 6.4 days
- Estimate to complete future years
- 0.0 days