December Report
- Report Date
- December 2015
Achievements in Last Period
- Initial Build review completed
- Peer Testing completed with no major issues highlighted, some minor changes to be implemented
Issues
- Integration Testing moved to 5th January due to Dev Tech resource on annual leave
- Questions raised about Student data relating to 'withdrawn status' has impacted the build review sign off this is in conjuction with data being passed to IDM / Grouper - this is being investigated by Dave Berry Enterpirse architect to provide guidance and gain agreement with Student Systems
- Grouper Upgrade to test happening on 5th Jan therefore will require this to take place before testing can commence
- Review budget as currently over initial 50 days this has been raised with Programme Manager
Next Steps
- Build Sign off
- Complete Integration testing
- UAT to commence
- Approved budget
- 50.0 days
- Activity this month
- 10.0 days
- Activity this year
- 38.0 days
- Activity to date
- 42.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days