November Report
- Report Date
- November 2015
Achievements in Last Period
System Design specification reviewed and signed off
Application and Data Architecture Document signed off by Dave Berry
Build activity underway, LDAP PHP extension installed on environments
User access provided for LDAP / Grouper in preparation for UAT
LDAP / Grouper overview completed for project team
SSP have provided feedback on BRD and SDS, updates to be provided back by Service Manager and Developer
Issues
- Review developments being completed via COM021 which may have an impact on TEL025 for Grouper changes
Next Steps
Complete Build and Peer Test
Build review and Sign off
Integration Testing to complete
Preparation for UAT
- Approved budget
- 50.0 days
- Activity this month
- 12.5 days
- Activity this year
- 28.5 days
- Activity to date
- 32.2 days
- Estimate to complete current year
- 21.2 days
- Estimate to complete future years
- 0.0 days