October Report

Report Date
October 2015

Achievements in Last Period

  • Application and Data Architecture Document completed
  • New process flow documented
  • Business Requirements provided by Service Manager have been documented, reviewed and final sign off provided by business area
  • Draft UAT plan created
  • System Design specification now available for review and sign off based on BRD now signed off
  • Design review scheduled for 3rd Nov

Issues

  • Completion of BRD delayed due to PM on unexpected leave and Service Manager not able to progress, system Design has been completed in parallel with requirements so no impact on design milestone
  • Dev Tech resource reallocated as original resource now leaving team – delay to TAD being updated
  • Design under review by Applications Architectural group; budget and estimates to be reviewed subject to technical approach, expect build days to be circa 10 days as no new interface required as solution proposed is using LDAP (Grouper)

Next Steps

  • BRD and Design Approval
  • Commence build activity

The project status is GREEN

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
5.0 days
Activity this year
15.0 days
Activity to date
19.5 days
Estimate to complete current year
38.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Moodle Course Enrolment Management
Code
TEL025
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
20-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Sep-2016
Overall Priority
Normal
Category
Discretionary