June report

Report Date
June 2016

Achievements in Last Period

  • New test data available for UAT from SSP and testing completed for key functionality
  • System Design Document created and handed to Application Management
  • Handover to Production Management
  • Preparation for deployment – service alert etc.

 

Issues

  • UAT extended due to some test data quality issues and business team not comfortable with volume of data, therefore deployment scheduled for 29th June delayed to allow project team to review options for deployment
  • Options to enable deployment to live - perferred option to complete a softlaunch of a small number of SEM1 courses and monitor data quality for 4 weeks to allow project to complete closure. Full launch for SEM2 courses later in the year.
  • New dates being agreed and review of budget as it will require carry over budget into 16/17 estimated at 4 days to cover deployment support and closure
  • Development work aligned to Course Code fix being completed via ITS RDS Service Management budget requires resource top start work as key developer not available until August

Next Steps

  • Sign off Acceptance
  • Deployment to Live (Soft Launch - 10 courses SEM1)
  • Monitoring Data Quality following Soft Launch

 

The project status is AMBER due to delay in UAT sign off and Deployment date changed

12-Jul-2016

Acceptance complete

19-Jul-2016

Deployment complete

16-Aug-2016

Deployment Review complete

30-Aug-2016

Closure

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
80.0 days
Activity this month
4.3 days
Activity this year
72.3 days
Activity to date
76.4 days
Estimate to complete current year
7.2 days
Estimate to complete future years
4.0 days

Project Info

Project
Moodle Course Enrolment Management
Code
TEL025
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
20-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Sep-2016
Overall Priority
Normal
Category
Discretionary