May Report

Report Date
May 2016

Achievements in Last Period

  • Commence development work aligned to Course Code fix is being  progressed alongside TEL025 but being charged via ITS RDS Service Management budget
  • Test environment being prepped for UAT to commence following upgrade
  • New test data requested for commencement of UAT from SSP
  • Dev Tech resource aligned to new milestone dates

 Issues

  • UAT due to recommence week starting 23rd May, following Moodle upgrade on test via TEL030 project. Unfortunately delayed until 7th June due to key TEL030 resource being off on leave
  • Review completed on impacts of delays on project budget and milestones with project PICCL raised and submitted to WIS

Next Steps

  • Sign off Acceptance
  • Preparation for deployment – checklist, service alert etc.
  • Deployment to Live

 

The project status is GREEN

21-Jun-2016Acceptance completeAccept
28-Jun-2016Deployment completeDeliver
12-Jul-2016Deployment Review completeDeliver
19-Jul-2016ClosureClose
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
2.5 days
Activity this year
67.5 days
Activity to date
72.5 days
Estimate to complete current year
10.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Moodle Course Enrolment Management
Code
TEL025
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
20-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Sep-2016
Overall Priority
Normal
Category
Discretionary