May Report
- Report Date
- May 2016
Achievements in Last Period
- Commence development work aligned to Course Code fix is being progressed alongside TEL025 but being charged via ITS RDS Service Management budget
- Test environment being prepped for UAT to commence following upgrade
- New test data requested for commencement of UAT from SSP
- Dev Tech resource aligned to new milestone dates
Issues
- UAT due to recommence week starting 23rd May, following Moodle upgrade on test via TEL030 project. Unfortunately delayed until 7th June due to key TEL030 resource being off on leave
- Review completed on impacts of delays on project budget and milestones with project PICCL raised and submitted to WIS
Next Steps
- Sign off Acceptance
- Preparation for deployment – checklist, service alert etc.
- Deployment to Live
The project status is GREEN
21-Jun-2016 | Acceptance complete | Accept |
28-Jun-2016 | Deployment complete | Deliver |
12-Jul-2016 | Deployment Review complete | Deliver |
19-Jul-2016 | Closure | Close |
- Approved budget
- 80.0 days
- Activity this month
- 2.5 days
- Activity this year
- 67.5 days
- Activity to date
- 72.5 days
- Estimate to complete current year
- 10.1 days
- Estimate to complete future years
- 0.0 days