July Report
- Report Date
- July 2015
Achievements in Last Period
- Project initiated and website created
- Project manager allocated
- Initial discussion held with ISG Resource Manager and Developer to provide update on R&D activities to date
- Initial discussion held with Stephanie Hay regarding business requirements and project timescales and milestones
Issues
- Review budget effort position (100 days) with Programme Manager and Project Sponsor on how funding has been allocated across 14/15 (20 days) 15/16 (50 days) and 16/17 (30 days) as noted in ASTA Request for Project Start
Next Steps
- Planning and Resource Estimates
- Project Brief approval
The project status is GREEN
14-Aug-2015 | Project Brief completed |
- Approved budget
- 100.0 days
- Activity this month
- 4.0 days
- Activity this year
- 4.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 96.0 days