July Report

Report Date
July 2015

Achievements in Last Period

  • Project initiated and website created
  • Project manager allocated
  • Initial discussion held with ISG Resource Manager and Developer to provide update on R&D activities to date
  • Initial discussion held with Stephanie Hay regarding business requirements and project timescales and milestones

 

Issues

  • Review budget effort position (100 days) with Programme Manager and Project Sponsor on how funding has been allocated across 14/15 (20 days) 15/16 (50 days) and 16/17 (30 days) as noted in ASTA Request for Project Start

 

Next Steps

  • Planning and Resource Estimates
  • Project Brief approval

 

The project status is GREEN

 

14-Aug-2015Project Brief completed
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
4.0 days
Activity this year
4.0 days
Activity to date
4.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
96.0 days

Project Info

Project
Moodle Course Enrolment Management
Code
TEL025
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
20-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Sep-2016
Overall Priority
Normal
Category
Discretionary