Report for November 2019
- Report Date
- November 2019
Achievements this period
- A workshop was held with stakeholders from Communications and Marketing, Website and Communications, Software Development and Colleges; to consider the use of Drupal as a solution and to discuss the wider vision and business requirements.
- Follow on questions have since been issued that will need to be answered by the business in order to properly assess business needs.
- Use Stories have also been written to allow a business focus on relevance and prioritisation.
Issues
-
Non-availability of business resource due to strike action.
-
No forward plan to compensate for loss of the Project Manager in January should project extend beyond this period (reason for reporting a RAG status of RED).
-
Project milestones have been missed and need to be re-planned.
Next steps
- Raise Change Request to get project back into governance.
- Workshop scheduled for the 13th December.
- Options appraisal paper to be produced for review.
- Approved budget
- 35.0 days
- Activity this month
- 2.5 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days