Report for July 2019
- Report Date
- July 2019
Report for July 2019 by Ken Miller
Achievements
- Project funding has been agreed with USG to fund the software purchase and ISG to fund the effort.
- Milestones rescheduled in response to delay caused by lack of funding agreement.
- Project Brief raised at WIS but not approved.
- Product evaluation completed and preferred solution identified as eCase from Fivium.
- Access to preferred solution provided for equality access assessment and report produced.
Issues
Next Steps
- Project Brief raised and approved.
- Assist with with the production and sign off of DPIA
- Assist with with the production and sign off of EqIA assessment and liaise with eCase regarding access recommendations.
- Engage with Procurement regarding process to purchase preferred solution.
Milestones
Rescheduled dates yet to be approved by WIS are:
Target Date![]() |
Title | Stage |
---|---|---|
21-May-2019 | Go/No Go Budget Approval | Plan |
26-Jul-2019 | End of Planning | Plan |
26-Jul-2019 | Product Evaluation | Analyse |
30-Aug-2019 | Product Procurement | Procure |
25-Oct-2019 | Product Implementation | Build |
08-Nov-2019 | User Acceptance Testing - Sign Off | Accept |
22-Nov-2019 | Go Live | Deliver |
06-Dec-2019 | Deployment Sign Off | Deliver |
13-Dec-2019 | Migration of Historic Data | Deliver |
13-Dec-2019 | Legacy ColdFusion Decommissioned | Deliver |
20-Dec-2019 | Project Closure | Close |
- Approved budget
- 120.0 days
- Activity this month
- 4.6 days
- Activity this year
- 23.1 days
- Activity to date
- 23.1 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 70.0 days