Report for May 2019
- Report Date
- May 2019
Report for May 2019 by Ken Miller
Achievements
- Project brief completed for approval .
- Final solution demonstration and hands on afternoon session held.
- On-going evaluation of all 3 proposed solutions.
- Disability Information Officer contacted regarding accessibility testing.
Issues
- Budget approval for the project remains outstanding. This is being escalated.
Next Steps
- Project Brief raised and approved.
- On-going evaluation and preferred solution identified.
- Engage with Procurement regarding process to purchase preferred solution.
- Raise paper regarding project budget and confirmation of availability.
Milestones
To be confirmed
Target Date![]() |
Title | Stage |
---|---|---|
21-May-2019 | Go/No Go Budget Approval | Plan |
31-May-2019 | End of Planning | Plan |
07-June-2019 | Product Evaluation | Analyse |
04-Jul-2019 | Product Procurement | Procure |
05-Aug-2019 | Product Implementation | Build |
23-Aug-2019 | User Acceptance | Accept |
06-Sept-2019 | Go Live | Deliver |
04-Oct-2019 | Deployment Sign Off | Deliver |
25-Oct-2019 | Migration of Historic Data | Deliver |
15-Nov-2019 | Legacy ColdFusion Decommissioned | Deliver |
29-Nov-2019 | Project Closure | Close |
- Approved budget
- 120.0 days
- Activity this month
- 7.2 days
- Activity this year
- 14.2 days
- Activity to date
- 14.2 days
- Estimate to complete current year
- 59.3 days
- Estimate to complete future years
- 45.0 days