Report for April 2019
- Report Date
- April 2019
Report for April 2019 by Ken Miller
Achievements
- Project brief on-going but not yet completed for approval.
- Initial two solution demonstrations held.
- Access gained to trial environments and Records Management carrying out evaluation exercise.
- Disability Information Officer contacted regarding accessibility testing.
Issues
- A Go/No Go milestone to be included prior to Planning sign off to confirm budget available for 2019/20.
Next Steps
- Project Brief raised and approved.
- Final Product demonstration held.
- On-going evaluation of proposed solutions.
- Engage with replacement procurement contact as a result of previous contact leaving the university.
Milestones
To be agreed
- Approved budget
- 0.0 days
- Activity this month
- 5.6 days
- Activity this year
- 7.0 days
- Activity to date
- 6.8 days
- Estimate to complete current year
- 66.0 days
- Estimate to complete future years
- 45.0 days