Report for March 2019
- Report Date
- March 2019
Report for March2019 by Ken Miller
Achievements
- ASTA combined project request form raised.
- Initial engagements with Records Management regarding G-Cloud evaluation process.
- On-going engagement with Procurement now that a G-Cloud procurement has been agreed.
Issues
- A Go/No Go milestone to be included prior to Planning sign off to confirm budget available for 2019/20.
Next Steps
- Project Brief raised and approved.
- Initial product evaluation commenced.
Milestones
To be agreed
- Approved budget
- 0.0 days
- Activity this month
- 1.3 days
- Activity this year
- 1.3 days
- Activity to date
- 1.3 days
- Estimate to complete current year
- 63.0 days
- Estimate to complete future years
- 25.0 days