Report for October 2016
- Report Date
- October 2016
Achievements:
- Update draft brief
Issues:
-
Planning delayed due to competing priorities and PM leave. WIS approve change in planning milestone on 21 October 2016, see issue 1.
Next Steps:
- Complete Project planning
Next Milestone:
Project brief to be completed by 11 November 2016
- Approved budget
- 250.0 days
- Activity this month
- 0.6 days
- Activity this year
- 9.2 days
- Activity to date
- 15.4 days
- Estimate to complete current year
- 200.6 days
- Estimate to complete future years
- 34.0 days