Report for November 2018

Report Date
November 2018

Achievements this period

Technical issues with Funnelback search engine have not been overcome and the use of Funnelback has been reviewed and removed from the solution.

Whilst this is a significant change to the overall technical solution, alternative products  have been substituted to achieve the desired search functionality.

With the data challenges with Pure profiles and the inconsistencies across Schools EdWeb profiles,  the search results currently returned are profiles showing academic areas of expertise rather than Pd.D specifics.  Search results are an overestimated guess of academics that may or may not be willing to supervise.  These results are not be suitable for a prospective student journey.  Until there is a fit for purpose staff database there is no appetite to deploy the search tool in production at this time.

A revised design and proof on concept (POC) using the alternative products has been built.  This PoC is to be used purely as a demonstrator by the sponsor to influence and support driving data quality and consistency in Pure data profiles.

To deploy the demonstrator a new front end design and build are required.  Dev Services have been consulted and a revised set of requirements will be submitted in due course.

SEP are in the process of building a project to that will consider some aspects of these challenges and this is expected to feed into the overall goals of Student Recruitment.   In terms of search capability SEP will potentially take the POC to the next level in terms of developing the solution further. This would require a project to complete the necessary tasks.

A PICCL has been raised to reflect the scope and milestone changes.

Issues

  • None

Next steps

  • Provide requirements to support revised front end design
  • Request necessary resources to complete the design and deployment of the POC

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver Yes
25-Jan-2019 No date available Design Design No
08-Feb-2019 No date available Build Build No
28-Feb-2019 No date available Project Closure Close No
         
External Milestones        
21-Dec-2018 21-Dec-2017 Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available"         
21-Dec-2018 11-May-2017 Guidance policy for use and tagging of keywords to support PGR search
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
5.6 days
Activity this year
8.9 days
Activity to date
8.9 days
Estimate to complete current year
11.1 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation