Report for May 2018

Report Date
May 2018

Achievements this period

  • Business analysis work has been completed
  • Mock-up / Prototype built for demonstration to sponsor and Research Information Committee
  • Reconfirmed business requirements with sponsor
  • Project re-plan  completed 5th April 2018 and end of planning approved by WIS
  • Resources confirmed

Issues

  • None

Next steps

  • Continue with project tasks including API research and search engine preparatory work.

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design No
19-Jun-2018 No date available Build Complete Build No
03-Jul-2018 No date available Integration Complete Integrate                  No
18-Jul-2018 No date available Acceptance Complete Accept No
TBC No date available Deployment Deliver No
TBC No date available Project Closure Close No
         
External Milestones        
21-Dec-2018 21-Dec-2017 Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available"         
21-Dec-2018 11-May-2017 Guidance policy for use and tagging of keywords to support PGR search
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
126.0 days
Activity this month
6.9 days
Activity this year
21.6 days
Activity to date
44.8 days
Estimate to complete current year
40.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary