Report for April 2018

Report Date
April 2018

Achievements this period

  • Business analysis work has been updated  and refreshed
  • Mock-up / Prototype built for demonstration to sponsor and Research Information Committee
  • Reconfirmed business requirements with sponsor
  • Project re-plan  completed 5th April 2018
  • Dependencies on other projects removed
  • Project brief refreshed with a view to end of planning on 3rd May
  • Resource requests out with supplier areas

Issues

  • None

Next steps

  • Complete end of planning  to be signed-off through quality assurance process
  • Agree final resourcing for work to complete before end of academic year

Milestones

13-Apr-2018 End of Planning (re-plan following suspension)
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
126.0 days
Activity this month
5.1 days
Activity this year
12.8 days
Activity to date
37.9 days
Estimate to complete current year
87.2 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary