Report for April 2018
- Report Date
- April 2018
Achievements this period
- Business analysis work has been updated and refreshed
- Mock-up / Prototype built for demonstration to sponsor and Research Information Committee
- Reconfirmed business requirements with sponsor
- Project re-plan completed 5th April 2018
- Dependencies on other projects removed
- Project brief refreshed with a view to end of planning on 3rd May
- Resource requests out with supplier areas
Issues
- None
Next steps
- Complete end of planning to be signed-off through quality assurance process
- Agree final resourcing for work to complete before end of academic year
Milestones
| 13-Apr-2018 | End of Planning (re-plan following suspension) |
- Approved budget
- 126.0 days
- Activity this month
- 5.1 days
- Activity this year
- 12.8 days
- Activity to date
- 37.9 days
- Estimate to complete current year
- 87.2 days
- Estimate to complete future years
- 0.0 days