Report for March 2018
- Report Date
- March 2018
Achievements this period
- New PM appointed
- Engaged with project sponsor and restated high level business requirements
- Project re-plan underway and expected 5th April 2018
Issues
- End of planning milestone has been missed. A re-plan is required to bring the project back into governance and an issue has been raised.
Next steps
- Publish revised plan and revised project brief and agree with stakeholders to be signed-off through quality assurance process
Milestones
| 23-Mar-2018 | End of Planning (re-plan following suspension) |
- Approved budget
- 126.0 days
- Activity this month
- 0.4 days
- Activity this year
- 6.0 days
- Activity to date
- 31.1 days
- Estimate to complete current year
- 94.9 days
- Estimate to complete future years
- 0.0 days