Report for February 2018
- Report Date
- February 2018
Achievements this period
- Project restarted
- New PM appointed
Issues
- Project needs to be re-planned
Next steps
- Re-planning
- Revised brief and plan agreed with stakeholders and signed off through quality assurance process
Milestones
| 23-Mar-2018 | End of Planning (re-plan following suspension) |
- Approved budget
- 126.0 days
- Activity this month
- 2.4 days
- Activity this year
- 5.6 days
- Activity to date
- 30.7 days
- Estimate to complete current year
- 94.8 days
- Estimate to complete future years
- 0.0 days