Report for August 2016

Report Date
August 2016

Achievements this period

Issues

  • None at this early stage in project planning

Next steps

  • Complete Project planning
  • Governance is sought from RASG. The project brief will be shared with them ahead of their meeting on 18 November 2016.

Milestones

  • Project brief to be completed by 30 September 2016

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
250.0 days
Activity this month
6.1 days
Activity this year
6.1 days
Activity to date
12.2 days
Estimate to complete current year
203.8 days
Estimate to complete future years
34.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation