- Report Date
- August 2016
Achievements this period
Issues
- None at this early stage in project planning
Next steps
- Complete Project planning
- Governance is sought from RASG. The project brief will be shared with them ahead of their meeting on 18 November 2016.
Milestones
- Project brief to be completed by 30 September 2016
- Approved budget
- 250.0 days
- Activity this month
- 6.1 days
- Activity this year
- 6.1 days
- Activity to date
- 12.2 days
- Estimate to complete current year
- 203.8 days
- Estimate to complete future years
- 34.0 days