Report for Feb 2019

Report Date
February 2019

Achievements in Last Period

  • Project has been suspended since 13-July 2018
  • The Business team have confirmed that they now have a viable alternative solution for reporting that has been built using Microsoft Power BI against the raw Worktribe BI Data extract to produce KPI reports and other useful reporting
  • The Business lead and project sponsor don't want to invest any more effort in the BI Suite universe solution
  • It is now proposed that the STU252 project is withdrawn
  • Draft closure report has been written

Issues

  • Open - Lessons learned to be documented in the closure report
  • Unresolved - UAT testing failed - could not get the figures to match in the BI Suite KPI reports and the existing KPI reports
  • Unresolved - UAT testing failed - could not replicate the user permissions model as implemented in the Worktribe application , in BI Suite.
    • Risk that BI suite users could get access to a wider set of data for other research projects that they were not entitled to see.
      • Workaround  of providing no org unit data restrictions to small group of super users / managers in the centre has been rejected by Business lead
      • Workaround explored with IS Service Management of applying row level permissions within BI Suite , but doesn't look like this would work for  IGMM and Roslin, nor would complex data structures with collaborative projects with multiple budgets for each Org unit

Next Steps 

 

  • Lessons learned meeting scheduled on Wed 13th March  - with Damon Querry, Kelvin Clark, Dave Berry , Danny Emerson, Geir Granum, John Chan, Jamie Thin - to feed into future BI / MI and Enterprise Data Warehouse projects
  • Complete final closure report and close project

Milestones

Closure Milestone - date updated

Project Status
RAG Status
Overall
BLUE
RAG Commentary
BLUE - Suspended, prior to being formally Withdrawn
Change Status
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe BI Suite Universe - Research Management BI/MI enhancements
Code
STU252
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
James Thin
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
11-Mar-2016
Planning Date
26-May-2016
Delivery Date
29-Mar-2019
Close Date
12-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary