April 2016

Report Date
April 2016

Achievements in Last Period

  • Complete server build
  • Install FileMaker Server

Issues

  • None this period 

Next steps

  • UAT
  • DevTech to do the TAD & install the SSL certificate

 

Milestones

20-May-2016UAT Complete on trial version of Filemaker Server
03-Jun-2016SLA set up
08-Jun-2016Install to LIVE server
15-Jun-2016Acceptance Sign Off
22-Jun-2016Deployment Sign Off Review
07-Jul-2016Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
57.0 days
Activity this month
1.0 day
Activity this year
24.0 days
Activity to date
24.0 days
Estimate to complete current year
32.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LEAPS Pre-Application Enquiry Database
Code
STU249
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Laura Cattell
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary