April 2016
- Report Date
- April 2016
Achievements in Last Period
- Complete server build
- Install FileMaker Server
Issues
- None this period
Next steps
- UAT
- DevTech to do the TAD & install the SSL certificate
Milestones
| 20-May-2016 | UAT Complete on trial version of Filemaker Server |
| 03-Jun-2016 | SLA set up |
| 08-Jun-2016 | Install to LIVE server |
| 15-Jun-2016 | Acceptance Sign Off |
| 22-Jun-2016 | Deployment Sign Off Review |
| 07-Jul-2016 | Project Closure |
- Approved budget
- 57.0 days
- Activity this month
- 1.0 day
- Activity this year
- 24.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 32.0 days
- Estimate to complete future years
- 0.0 days