March 2016
- Report Date
- March 2016
Achievements in Last Period
- Plan for implementation agreed. New milestones added for installation, UAT and SLA set up
- Agreed date of the server build and install of Filemaker Server to be completed by 22/04/16.
- UAT agreed to commence after install as have 30 day evaluation for Filemaker Server.
Issues
- None this period
Next steps
- Complete server build
- Install FileMaker Server
- Commence UAT
Milestones
| 22-Apr-2016 | Server build and trial Filemaker install complete |
| 20-May-2016 | UAT Complete on trial version of Filemaker Server |
| 03-Jun-2016 | SLA set up |
| 08-Jun-2016 | Install to LIVE server |
| 15-Jun-2016 | Acceptance Sign Off |
| 22-Jun-2016 | Deployment Sign Off Review |
| 07-Jul-2016 | Project Closure |
- Approved budget
- 57.0 days
- Activity this month
- 3.0 days
- Activity this year
- 23.0 days
- Activity to date
- 23.0 days
- Estimate to complete current year
- 31.0 days
- Estimate to complete future years
- 0.0 days