March 2016

Report Date
March 2016

Achievements in Last Period

  • Plan for implementation agreed. New milestones added for installation, UAT and SLA set up
  • Agreed date of the server build and install of Filemaker Server to be completed by 22/04/16.
  • UAT agreed to commence after install as have 30 day evaluation for Filemaker Server.

 

Issues

  • None this period 

 

Next steps

  • Complete server build
  • Install FileMaker Server
  • Commence UAT

 

Milestones

22-Apr-2016Server build and trial Filemaker install complete
20-May-2016UAT Complete on trial version of Filemaker Server
03-Jun-2016SLA set up
08-Jun-2016Install to LIVE server
15-Jun-2016Acceptance Sign Off
22-Jun-2016Deployment Sign Off Review
07-Jul-2016Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
57.0 days
Activity this month
3.0 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
31.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LEAPS Pre-Application Enquiry Database
Code
STU249
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Laura Cattell
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary