Achievements in Last Period

  • Meeting was held with the business and a university staff member with FileMaker experience in order to get timescales at the end of December. They indicated that there would be a possibility that, subject to estimate and manager approval, they could complete the work required.

Issues

  • Cost RED: funding needed for a FileMaker consultant to carry out the installation of FileMaker Server and to set up or show how to set up individual users has not been approved
  • Time RED: the Plan for implementation agreed (including all milestones until Project Closure) milestone has not been achieved due to the lack of contractor funding. The is currently being pursued with a meeting with the business and a potential source to gauge potential cost. The business user and project manager will then agree a new plan with the project sponsor.

Next steps

  • FileMaker consultant to estimate the amount of work required on their part.
  • Business to determine whether funding for a FileMaker consultant can be provided. If not this project is at risk of not being able to make any further progress.
Project Status
RAG Status
Time
RED
Cost
RED
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
57.0 days
Activity this month
1.0 day
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
39.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LEAPS Pre-Application Enquiry Database
Code
STU249
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Laura Cattell
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2017
Programme Priority
2
Overall Priority
Normal