Report for July 2017
- Report Date
- July 2017
Achievements in Last Period
-
Install FileMaker Pro to machines in SRA - achieved
- Testing from Admissions Offices perspective (business) - achieved and signed off
- Complete Technical Architecture Document and handover - - achieved
- Closure report written and distributed. - achieved and signed off
- Closure agreed. - achieved
Issues
- None
Next steps
-
None
- Approved budget
- 60.0 days
- Activity this month
- 2.8 days
- Activity this year
- 6.2 days
- Activity to date
- 58.8 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days