Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
-
Set up SSL certificate complete
-
AD groups for managing accounts created
-
Consolidation of files into single database complete
-
Security and access review complete
Issues
- Business lead is on secondment to SEP, and was expected to be available again at the start of July. This is not the case, as key business activity for the summer schools will be undertaken and so she will not be available until mid-July, at the time when key technical resource has holiday.
Next steps
-
Active directory bind to Filemaker Server
-
Install FileMaker Pro to machines in SRA
- Testing from Admissions Offices perspective (business)
- Admissions officer training (business)
- Complete Technical Architecture Document
RAG Commentary
ISSUE - Open Business area resources not available to start UAT on schedule and so UAT start will be delayed to mid-July.
- Approved budget
- 60.0 days
- Activity this month
- 0.5 days
- Activity this year
- 21.0 days
- Activity to date
- 53.0 days
- Estimate to complete current year
- 6.6 days
- Estimate to complete future years
- 0.0 days