December 2016
- Report Date
- December 2016
Achievements in Last Period
- No activity in December - UAT is set to take place on 26 / 27th January. Trial version of FileMaker Server has 30 days to run, so this will need to be installed in January
Issues
- No Issues
Next steps
- FileMaker Server trial re-installed to co-inside with the Business Lead's available day. The person from ITI who did the original install is not available, so will need to organise someone from Dev Tech to do this.
- UAT sign off
- License purchased for FileMaker Server to make live
- TAD completed
Milestones
| 27-Jan-2017 | UAT Complete on trial version of Filemaker Server |
| 02-Feb-2017 | Install to LIVE server |
| 15-Feb-2017 | Deployment Sign Off Review |
| 24-Feb-2017 | Project Closure |
- Approved budget
- 57.0 days
- Activity this month
- 0.5 days
- Activity this year
- 9.0 days
- Activity to date
- 40.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days