December 2016

Report Date
December 2016

Achievements in Last Period

  • No activity in December - UAT is set to take place on 26 / 27th January. Trial version of FileMaker Server has 30 days to run, so this will need to be installed in January

Issues

  • No Issues

Next steps

  • FileMaker Server trial re-installed to co-inside with the Business Lead's available day. The person from ITI who did the original install is not available, so will need to organise someone from Dev Tech to do this.
  • UAT sign off
  • License purchased for FileMaker Server to make live
  • TAD completed

 

Milestones

27-Jan-2017 UAT Complete on trial version of Filemaker Server
02-Feb-2017 Install to LIVE server
15-Feb-2017 Deployment Sign Off Review
24-Feb-2017 Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
57.0 days
Activity this month
0.5 days
Activity this year
9.0 days
Activity to date
40.0 days
Estimate to complete current year
13.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LEAPS Pre-Application Enquiry Database
Code
STU249
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Laura Cattell
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary