November 2016
- Report Date
- November 2016
Achievements in Last Period
- Client PC Upgraded. This is now ready to connect to the new FileMaker Server install
Issues
- Been informed that the business lead is on secondment and will only have a small window to test. This has been identified as a couple of days at the end of January. The project sponsor has agreed that she is the only person that could test this, so milestones need to change.
- Project is RED because of the milestone changes
Next steps
- FileMaker Server trial re-installed to co-inside with the Business Lead's available day
- UAT sign off
- License purchased for FileMaker Server to make live
- TAD completed
Milestones
| 27-Jan-2017 | UAT Complete on trial version of Filemaker Server |
| 02-Feb-2017 | Install to LIVE server |
| 15-Feb-2017 | Deployment Sign Off Review |
| 24-Feb-2017 | Project Closure |
- Approved budget
- 57.0 days
- Activity this month
- 2.0 days
- Activity this year
- 8.0 days
- Activity to date
- 40.0 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days