July 2016
- Report Date
- July 2016
Achievements in Last Period
- Activity stalled last month due to annual leave / busy period for the business. They have requested the delay. Some unplanned carry-over of IS Apps effort into 16-17.
- No hard milestones for this project - so new milestones agreed
Issues
- No issues for July
- Milestones will be re-set - once the business confirm when they can complete remaining tasks
Next steps
- Client PC upgrade
- UAT sign off
- SLA set up
- License purchased for FileMaker Server
- Deploy to Live
- TAD completed
- Approved budget
- 57.0 days
- Activity this month
- 1.0 day
- Activity this year
- 31.0 days
- Activity to date
- 31.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 7.0 days