October 2015

Report Date
October 2015

Achievements in Last Period

  • No further action expected until after the wider CAM UG migration scheduled for 27-Oct-15 - continuing as planned.
  • The wider CAM UG migration on 27-Oct-15 went very smoothly and no development issues were raised, meaning the project will likely come in under the last estimate.

Issues

  • None.

Next steps

  • UG Deployment sign-off.
  • Decommission PG & UG Polopoly folders.
  • Project Closure.

Milestones

Target DateMilestone
06-Nov-2015UG - Deployment Sign off
20-Nov-2015Decommission PG & UG Polopoly folders
27-Nov-2015Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
74.0 days
Activity this month
1.0 day
Activity this year
18.0 days
Activity to date
63.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAM Enhancements to UG & PG Degree Finders
Code
STU247
Programme
Student Services (STU)
Project Manager
Sheila Fraser
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
24-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Nov-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary